NO.1 Which plan provides the Business Case with costs during the Initiating a Project process?
A. Initiation Stage Plan
B. Project Plan
C. Stage Plan
D. Team Plan
Answer: B

PRINCE2無料   PRINCE2-Foundation   PRINCE2-Foundationサービス   PRINCE2-Foundation正確率   PRINCE2-Foundationコマンド

NO.2 Which product documents the information needed to demonstrate continued business
justification?
A. Business Case
B. Communication Management Strategy
C. Project Product Description
D. Quality Management Strategy
Answer: A

PRINCE2一発合格   PRINCE2-Foundation試験時間   PRINCE2-Foundationキャッシュ   PRINCE2-Foundation過去問題

NO.3 Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying
out a risk response action to respond to a particular risk.
A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner
Answer: C

PRINCE2模試   PRINCE2-Foundation vue   PRINCE2-Foundation   PRINCE2-Foundation参考書

NO.4 Which is a purpose of the Controlling a Stage process?
A. Produce a Team Plan for the work to be assigned to a Team Manager
B. Select and implement actions that will resolve deviations from a plan within tolerance
C. Obtain approvals for products delivered in a Work Package
D. Update a Project Plan to incorporate the actuals from a Stage Plan
Answer: B

PRINCE2的中率   PRINCE2-Foundationサンプル問題集   PRINCE2-Foundation   PRINCE2-Foundation組織   PRINCE2-Foundation

NO.5 What theme provides all management levels within the project management team with
mechanisms for monitoring and control?
A. Progress
B. Change
C. Organization
D. Quality
Answer: A

PRINCE2資格トレーニング   PRINCE2-Foundation勉強の資料   PRINCE2-Foundationサンプル問題集   PRINCE2-Foundation模擬モード

NO.6 Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Answer: B

PRINCE2試験対策   PRINCE2-Foundation無料   PRINCE2-Foundation合格率

NO.7 Which should be provided by a project mandate?
A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan
Answer: A

PRINCE2   PRINCE2-Foundation   PRINCE2-Foundation取得   PRINCE2-Foundation

NO.8 Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
Answer: B

PRINCE2フリーク   PRINCE2-Foundation会場   PRINCE2-Foundation資格認定

PRINCE2のPRINCE2-Foundation認証試験のために少ないお金でよい成果を取られるのPass4Testのは最良の選択でございます。Pass4Testは例年試験内容を提供したあなたに後悔しないように価値があるサイトだけではなく、無料の一年更新サービスも提供するに最も賢明な選択でございます。


PRINCE2のPRINCE2-Foundation認定試験は今IT業界の人気試験で多くのIT業界の専門の人士がITの関連の認証試験を取りたいです。PRINCE2の認証試験の合格書を取ってから更にあなたのIT業界での仕事にとても助けがあると思います。


IT業種が新しい業種で、経済発展を促進するチェーンですから、極めて重要な存在だということを良く知っています。Pass4Testの PRINCE2のPRINCE2-Foundation試験トレーニング資料は高度に認証されたIT領域の専門家の経験と創造を含めているものです。その権威性は言うまでもありません。あなたはPass4Testの学習教材を購入した後、私たちは一年間で無料更新サービスを提供することができます。


PRINCE2-Foundation試験番号:PRINCE2-Foundation
試験科目:「PRINCE2 Foundation written Exam」
一年間無料で問題集をアップデートするサービスを提供いたします
最近更新時間:2015-08-18
問題と解答:全150問 PRINCE2-Foundation 前提条件

>> PRINCE2-Foundation 前提条件


 

「あきらめたら そこで試合終了ですよ」という『スラムダンク』の中の安西監督が言った名言があります。この文は人々に知られています。試合と同じ、試験もそのどおりですよ。試験に準備する時間が十分ではないから、PRINCE2-Foundation認定試験を諦めた人がたくさんいます。しかし、優秀な資料を利用すれば、短時間の準備をしても、高得点で試験に合格することができます。信じないでしょうか。Pass4Testの試験問題集はそのような資料ですよ。はやく試してください。


購入前にお試し,私たちの試験の質問と回答のいずれかの無料サンプルをダウンロード:http://www.pass4test.jp/PRINCE2-Foundation.html




nice!(0)  コメント(0)  トラックバック(0) 

nice! 0

コメント 0

コメントを書く

お名前:
URL:
コメント:
画像認証:
下の画像に表示されている文字を入力してください。

トラックバック 0

この広告は前回の更新から一定期間経過したブログに表示されています。更新すると自動で解除されます。